Sumner CountyFriday, November 13
Kinder Morgan's proposed 470-mile gas pipeline would begin in Sumner County
The Daily Hendersonville team
If you live in Sumner County, here's a project to know. Kinder Morgan's proposed Southeast Connector Project is a 470-mile natural gas pipeline that would begin here and cross 10 Tennessee counties. Sumner County would be the northern connection point for utilities. The company says it's still in the early stages of planning.
The pipeline would cross 10 Tennessee counties
- 470 miles
- of proposed pipeline
- 10
- Tennessee counties on the route
- About 760
- landowners the company has identified statewide
Sources: News Channel 5 Nashville, WKRN News 2
For now, the company is asking landowners for permission to survey. It says it's "not anywhere near easement negotiations." Smith County resident Chad Grandell says his family's dog boarding business sits on land the route would cross. WKRN reports Kinder Morgan says the project wouldn't cost taxpayers anything and would bring in millions in new tax revenue, while a petition among landowners has started.
- Route: Macon, Trousdale and Smith counties, south to Franklin and Marion
- Federal approval: still needed before anything gets built
- Public meetings: Kinder Morgan says it will hold them
Construction could start in late 2028 if the pipeline is approved
- 2027Kinder Morgan plans to apply for federal approval.
- Late 2028Construction could begin if the project is approved.
- Late 2030Natural gas could be flowing if the project is approved.
Source: News Channel 5 Nashville
Sources: News Channel 5 Nashville, WKRN News 2