Power & UtilitiesTop story
NES says old equipment is a big part of Old Hickory Village's outages and plans an upgrade
NES plans a bigger system after reported outages
- 14
- outages some residents report in 10 months
- 23.9 kV
- system planned to replace the area's 4 kV one
- 6 months
- of design work NES expects to spend
Source: WSMV
If you live in Old Hickory Village, those flickering lights have an explanation. At Tuesday's meeting with Nashville Electric Service, some residents said they have had at least 14 outages in the past 10 months. WKRN reports that NES blames much of it on the area's old 4 kV wires, poles and transformers. Storms, vegetation and trip-and-reclose activity, an automatic shutoff when a line is hit by a branch or wildlife, account for the rest.
The long-term fix is a 23.9 kV system with new poles, transformers, primary lines and service conductors. Council member Jeff Eslick said it's a capital project for the fiscal year that starts July 1, but NES still needs a construction plan and funding.
- Design: NES expects about six months
- Construction: after July 1, one circuit at a time
- Meanwhile: targeted tree trimming and pole inspections
- Residents want a plan for updates during upgrades and outages
NES would start construction after July 1
- JanuaryAn ice storm puts stress on the Old Hickory Village system.
- Nov. 10NES representatives meet residents at the Old Hickory Community Center.
- July 1The new fiscal year starts, and construction would begin sometime after.
Source: WSMV
“I don't think tonight's the end. I think tonight is really the beginning.”
Metro Councilmember Jeff Eslick